Part 123: Cost Baseline
(OUTPUT Project Cost Management: Determine Budget)
- The Cost Baseline is the approved version of the time-phased project budget (excluding management reserves)
- Can only be changed through a formal change control procedure
- Used as a basis for comparison to actual results
- Remember
- The Cost Baseline is the sum of the Work Package Cost Estimates (what the activities will cost) and the Contingency Reserve (accounts for known-unknowns). It is the same value as the sum of the Control Accounts
The Project Budget is the sum of the Cost Baseline and the Management Reserve (accounts for unknown-unknowns)