Part 128: Cost Forecasts

//Part 128: Cost Forecasts
Part 128: Cost Forecasts2022-08-21T03:59:06+00:00

Part 128: Cost Forecasts
(OUTPUT Project Cost Management: Control Costs)

  • The Cost Forecast is the Estimate at Completion
  • Estimate at Completion (EAC) is compared to the Budget at Completion (BAC) to see if the project is within the budget or if a change request is required