Part 140: Project Documents Updates
(OUTPUT Project Integration Management: Direct and Manage Project Work)
(OUTPUT Project Integration Management: Monitor and Control Project Work)
(OUTPUT Project Integration Management: Perform Integrated Change Control)
(OUTPUT Project Integration Management: Close Project or Phase)
(OUTPUT Project Scope Management: Define Scope)
(OUTPUT Project Scope Management: Create WBS)
(OUTPUT Project Scope Management: Validate Scope)
(OUTPUT Project Scope Management: Control Scope)
(OUTPUT Project Schedule Management: Sequence Activities)
(OUTPUT Project Schedule Management: Estimate Activity Durations)
(OUTPUT Project Schedule Management: Develop Schedule)
(OUTPUT Project Schedule Management: Control Schedule)
(OUTPUT Project Cost Management: Estimate Costs)
(OUTPUT Project Cost Management: Determine Budget)
(OUTPUT Project Cost Management: Control Costs)
(OUTPUT Project Quality Management: Plan Quality Management)
(OUTPUT Project Quality Management: Manage Quality)
(OUTPUT Project Quality Management: Control Quality)
(OUTPUT Project Resource Management: Plan Resource Management)
(OUTPUT Project Resource Management: Estimate Activity Resources)
(OUTPUT Project Resource Management: Acquire Resources)
(OUTPUT Project Resources Management: Develop Team)
(OUTPUT Project Resources Management: Manage Team)
(OUTPUT Project Resources Management: Control Resources)
(OUTPUT Project Communications Management: Plan Communications Management)
(OUTPUT Project Communications Management: Manage Communications)
(OUTPUT Project Communications Management: Monitor Communications)
(OUTPUT Project Risk Management: Identify Risks)
(OUTPUT Project Risk Management: Perform Qualitative Risk Analysis)
(OUTPUT Project Risk Management: Perform Quantitative Risk Analysis)
(OUTPUT Project Risk Management: Plan Risk Responses)
(OUTPUT Project Risk Management: Implement Risk Responses)
(OUTPUT Project Risk Management: Monitor Risks)
(OUTPUT Project Procurement Management: Plan Procurement Management)
(OUTPUT Project Procurement Management: Conduct Procurements)
(OUTPUT Project Procurement Management: Control Procurements)
(OUTPUT Project Stakeholder Management: Identify Stakeholders)
(OUTPUT Project Stakeholder Management: Manage Stakeholder Engagement)
(OUTPUT Project Stakeholder Management: Monitor Stakeholder Engagement)

  • Project Documents Updates are always outputs
  • There are many types of Project Documents that can be updated
  • The most common are
    • Assumptions Log
      • We discover new assumptions and changes to existing assumptions, which must be recorded
    • Issue Log
      • Issues that arise during the process
    • Lessons Learned Register
      • Lessons we learned
    • Risk Register
      • Response strategies
      • Triggers
      • Budget and schedule activities required to respond to the risk
      • Risks that will remain after the risk response has been implemented
      • Secondary risks that occur after we have implemented the risk response
    • Risk Report
      • Assessment of overall project risk exposure
      • Chances of project success
      • Degree of variability remaining within the project
      • Detailed analysis of the project
      • Amount of contingency reserve needed
      • Identification of individual project risks
      • Trends in quantitative risk analysis
      • Recommended risk responses
  • May update the following documents
    • Direct and Manage Project Work
      • Activity List
      • Assumption Log
      • Lessons Learned Register
      • Requirements Documentation
      • Risk Register
      • Stakeholder Register
    • Monitor and Control Project Work
      • Cost Forecasts
      • Issue Log
      • Lessons Learned Register
      • Risk Register
      • Schedule Forecasts
    • Perform Integrated Change Control
      • Any document subject to the project’s formal change control process
    • Close Project or Phase
      • Any document that needs to be updated, especially the lessons learned register
    • Define Scope
      • Assumption Log
      • Requirements Documentation
      • Requirements Traceability Matrix
    • Create WBS
      • Project Scope Statement
      • Requirements Documentation
    • Validate Scope
      • Lessons Learned Register
      • Requirements Documentation
      • Requirements Traceability Matrix
    • Control Scope
      • Lessons Learned Register
      • Requirements Documentation
      • Requirements Traceability Matrix
    • Sequence Activities
      • Activity Attributes
      • Activity Lists
      • Assumption Log
      • Milestone List
      • Risk Register
    • Estimate Activity Durations
      • Activity Attributes
      • Assumptions Log
      • Lessons Learned Register
    • Develop Schedule
      • Activity Attributes
      • Assumption Log
      • Duration Estimates
      • Lessons Learned Register
      • Resource Requirements
      • Risk Register
    • Control Schedule
      • Assumption Log
      • Basis of Estimates
      • Lessons Learned Register
      • Project Schedule
      • Resource Calendars
      • Risk Register
      • Schedule Data
    • Estimate Costs
      • Assumption Log
      • Lessons Learned Register
      • Risk Register
    • Determine Budget
      • Cost Estimates
      • Project Schedule
      • Risk Register
    • Control Costs
      • Assumption Log
      • Basis of Estimates
      • Cost Estimates
      • Lessons Learned Register
      • Risk Register
    • Plan Quality Management
      • Lessons Learned Register
      • Requirements Traceability Matrix
      • Risk Register
      • Stakeholder Register
    • Manage Quality
      • Issue Log
      • Lessons Learned Register
      • Risk Register
    • Control Quality
      • Issue Log
      • Lessons Learned Register
      • Risk Register
      • Test & Evaluation Documents
    • Plan Resource Management
      • Assumption Log
      • Risk Register
    • Estimate Activity Resources
      • Activity Attributes
      • Assumption Log
      • Lessons Learned Register
    • Acquire Resources
      • Lessons Learned Register
      • Project Schedule
      • Resource Breakdown Structure
      • Resource Requirements
      • Risk Register
      • Stakeholder Register
    • Develop Team
      • Lessons Learned Register
      • Project Schedule
      • Project Team Assignments
      • Resource Calendars
      • Team Charter
    • Manage Team
      • Issue Log
      • Lessons Learned Register
      • Project Team Assignments
    • Control Resources
      • Assumption Log
      • Issue Log
      • Lessons Learned Register
      • Physical Resource Assignments
      • Resource Breakdown Structure
      • Risk Register
    • Plan Communications Management
      • Project Schedule
      • Stakeholder Register
    • Manage Communications
      • Issue Log
      • Lessons Learned Register
      • Project Schedule
      • Risk Register
      • Stakeholder Register
    • Monitor Communications
      • Issue Log
      • Lessons Learned Register
      • Stakeholder Register
    • Identify Risks
      • Assumption Log
      • Issue Log
      • Lessons Learned Register
    • Perform Qualitative Risk Analysis
      • Assumption Log
      • Issue Log
      • Risk Register
      • Risk Report
    • Perform Quantitative Risk Analysis
      • Risk Report
    • Plan Risk Responses
      • Assumption Log
      • Cost Forecast
      • Lessons Learned Register
      • Project Schedule
      • Project Team Assignments
      • Risk Register
    • Implement Risk Responses
      • Issue Log
      • Lessons Learned Register
      • Project Team Assignments
      • Risk Register
      • Risk Report
    • Monitor risks
      • Assumption Log
      • Issue Log
      • Lessons Learned Register
      • Risk Register
      • Risk Report
    • Plan Procurement Management
      • Lessons Learned Register
      • Milestone List
      • Requirements Documentation
      • Requirements Traceability Matrix
    • Conduct Procurement
      • Lessons Learned Register
      • Requirements Documentation
      • Requirements Traceability Matrix
      • Resource Calendars
      • Risk Register
      • Stakeholder Register
    • Control Procurement
      • Lessons Learned Register
      • Resource Requirements
      • Requirements Traceability Matrix
      • Risk Register
      • Stakeholder Register
    • Identify Stakeholders
      • Assumption Log
      • Issue Log
      • Risk Register
    • Manage Stakeholder Engagement
      • Change Log
      • Issue Log
      • Lessons Learned Register
      • Stakeholder Register
    • Monitor Stakeholder Engagement
      • Issue Log
      • Lessons Learned Register
      • Risk Register
      • Stakeholder Register