Part 191: Schedule Data
(OUTPUT Project Schedule Management: Develop Schedule)
- The Schedule Data is part of the project schedule model
- The data describes and controls the schedule
- Includes
- Milestones
- Schedule activities
- Activity attributes
- Documentation of the assumptions and constraints
- May also include
- Resource requirements by time period (in a histogram)
- Alternative schedules (best-case, worst-case, not-resource leveled)
- Scheduling of contingency reserves
- Delivery schedules