Part 70: Cost Aggregation
(Project Cost Management: Determine Budget)

  • It is difficult to estimate the total cost of the project, especially a large project
  • That is why we cut it up into small pieces, called Work Packages, in the Work Breakdown Structure
  • We estimate the cost of each work package, one by one
  • Then we add up all of the estimates