Summary of Financial Terms

AbbreviationNameDefinitionHow UsedEquationsInterpretation of Result
PVPlanned ValueThe authorized budget for the workThe value of the work planned to be completed at a point in time  
EVEarned ValueThe measure of work performed expressed in terms of budget authorized for the workPlanned value of the work completed to a point in time, without reference to actual costsEV = sum of the planned value of completed work 
ACActual CostThe actual cost incurred for the work performed during a specific time periodThe actual cost of all the work completed to a point in time  
BACBudget at CompletionThe sum of all budgets established for the work to be performedThe value of the total planned work; the project cost baseline  
CVCost VarianceThe amount of budget deficit or surplus at a given point in time, calculated as the difference between the earned value and actual costThe difference between the value of the work completed, and the actual costsCV = EV – ACPositive = Under planned cost Neutral = On Cost Negative = Over planned cost
SVSchedule VarianceThe amount by which the project is ahead or behind the planned delivery date, at a given point in time, calculated as the difference between the earned value and the planned valueThe difference between the work completed at a point in time and the work planned to be completed at the same point in timeSV = EV – PVPositive = Ahead of schedule Neutral = On Schedule Negative = Behind Schedule
VACVariance at CompletionProjection of the amount of budget deficit or surplus, calculated as the difference between the budget at completion and the estimate at completionEstimated difference in cost at the end of the projectVAC = BAC – EACPositive = Under planned Cost Neutral = On planned Cost Negative = Over planned Cost
CPICost Performance IndexMeasure of the efficiency of budgeted resources; calculated as the ratio of earned value to actual cost CPI = EV/ACGreater than 1.0 = under planned cost Exactly 1.0 = on planned cost Less than 1.0 = over planned cost
SPISchedule Performance IndexSchedule efficiency expressed as the ratio of earned value to planned value SPI = EV/PVGreater than 1.0 = ahead of schedule Exactly 1.0 = On schedule Less than 1.0 = Behind schedule
EACEstimate at CompletionExpected total cost of completing all work; calculated as the cost of the actual work plus the estimate to completeIf CPI is expected to stay the same until the project is completeEAC = BAC/CPI 
   If future work will be at the planned rateEAC = AC + BAC – EV 
   If initial plan is no longer validEAC = AC + Bottom-up ETC 
   If both CPI and SPI influence the remaining workEAC = AC + [(BAC – EV)/(CPI + SP)] 
ETCEstimate to CompleteThe expected cost to complete the remaining project work.Assuming work is on plan, the cost of completing workETC = EAC – AC 
   Reestimate the remaining work from the bottom upETC = Reestimate 
TCPITo Complete Performance IndexA measure of the cost performance that must be achieved with the remaining resources in order to meet the goalThe efficiency that must be maintained to complete the work on planTCPI = (BAC – EV) / (BAC – AC)Over 1.0 = Harder to complete Exactly 1.0 = Same to complete Less than 1.0 = Easier to complete